Agency for Nuclear Projects: Legal Cases


Legal Documents

Federal documents on these pages are not remediated. Please select the icon to the right of the document name to request document remediation assistance.

    Nuclear Regulatory Commission

    NEVADA REQUEST TO LIFT THE SUSPENSION OF THE ADJUDICATORY PROCEEDING FOR LIMITED PURPOSES

    NUREG-2184

    State of Nevada vs United States Environmental Agency

    Nevada v. United States Environmental Protection Agency (EPA) (U.S. Court of Appeals for the District of Columbia Circuit, No. 08-1327). Nevada filed suit on October 10, 2008, against EPA, challenging the revised EPA radiation standard for the proposed Yucca Mountain repository. Due to uncertainty at the federal level and the failure of Congress to fund the Yucca Mountain project, this litigation is being held in abeyance. In the event the adjudicatory portion of the NRC licensing proceeding resumes, or circumstances require, a restart of this litigation may be considered. Quarterly status reports continue to be filed with the Court.

    State of Nevada vs United States Nuclear Regulatory Commission

    Nevada v. United States Nuclear Regulatory Commission (NRC) (U.S. Court of Appeals for the District of Columbia Circuit, No. 09- 1133) Nevada filed a petition for judicial review on May 8, 2009, of the NRC’s Licensing Rule adopting EPA’s radiation standard for the proposed Yucca Mountain repository. The case is pending. This litigation is being held in abeyance pending resolution of whether the Yucca Mountain project will proceed and receive federal appropriations. In the event the adjudicatory portion of the NRC licensing proceeding resumes, or circumstances require, a restart of this litigation may be considered. Quarterly status reports continue to be filed with the Court.

    State of Nevada vs United States Department of Energy

    Nevada v. United States Department of Energy (9th Circuit 09 71015). This case challenges DOE’s selection of the Caliente rail corridor and currently is being held in abeyance pending congressional funding or as circumstances require.

      United States vs State Engineer

      United States v. State Engineer (5th Judicial District Court, Nye County, No. 15722). This is the appeal filed by the United States on behalf of the U.S. Department of Energy (DOE) following the State Engineer's denial of DOE’s applications for permanent water rights to construct and operate the proposed Yucca Mountain repository. This case was filed as a protective measure while the United States pursues its constitutional claims in the main water litigation in federal district court. The case remains pending.

        United States vs State of Nevada

        United States v. State of Nevada (U.S. District Court, No. CV-S-00-0268-DWH-LRL). This case is the United States’ challenge of the Nevada State Engineer's decision determining that DOE is not entitled to permanent water rights to construct and operate the proposed repository based on the State Engineer's finding that the proposed use threatens to be detrimental to the public interest. DOE curtailed its minimal water use and in 2009, publicly announced that the proposed Yucca Mountain High-Level Nuclear Waste repository is unworkable. At the present time, Congress has not appropriated funds for that purpose. The litigation remains pending.